Longest Paths and Schedules ​

Download notebookThe same code as on this page, ready to run in Jupyter with IJulia.

A project is a set of tasks, each with a duration, and a set of precedences: a task can start only when the tasks before it are done. The earliest a task can start is the length of the longest chain of work that leads to it, and the project's length is the longest chain of all, the critical path. In the max-plus semiring ( ,   ) the star of the precedence graph holds all of these longest paths at once.

A Small Project ​

Building a house: each arc a → b means b starts after a is done, and its weight is the duration of a, in days. Two zero-length tasks, start and finish, mark the ends of the project.

julia
using PATHPACK, SparseArrays, Random
using PATHPACK.CPU: MaxPlus, mstar

tasks = ["start", "permits", "foundation", "framing", "roof", "plumbing",
    "electrical", "insulation", "drywall", "paint", "floors", "finish"]
days = [0, 5, 7, 10, 4, 6, 5, 3, 6, 3, 4, 0]
after = [("start", "permits"), ("permits", "foundation"),
    ("foundation", "framing"), ("framing", "roof"), ("framing", "plumbing"),
    ("framing", "electrical"), ("roof", "insulation"),
    ("plumbing", "insulation"), ("electrical", "insulation"),
    ("insulation", "drywall"), ("drywall", "paint"), ("drywall", "floors"),
    ("paint", "finish"), ("floors", "finish")]

id = Dict(t => i for (i, t) in enumerate(tasks))
n = length(tasks)
src = [id[a] for (a, b) in after]
dst = [id[b] for (a, b) in after]
A = sparse(src, dst, Float64.(days[src]), n, n);

Every Longest Path ​

L[i, j] is the length of the longest chain of work from the start of i to the start of j, and -Inf (the semiring's zero) when j does not depend on i.

julia
L = mstar(MaxPlus(), A)
s, f = id["start"], id["finish"]
L[s, f]    # the project takes this many days
41.0

Row s holds the earliest start of every task, and column f the length of the work that must follow each task (its own duration included). A task's slack is how long it can slip without delaying the project; the tasks with no slack form the critical path.

julia
earliest = L[s, :]
slack = L[s, f] .- earliest .- L[:, f]
[tasks earliest slack]
12×3 Matrix{Any}:
 "start"        0.0  0.0
 "permits"      0.0  0.0
 "foundation"   5.0  0.0
 "framing"     12.0  0.0
 "roof"        22.0  2.0
 "plumbing"    22.0  0.0
 "electrical"  22.0  1.0
 "insulation"  28.0  0.0
 "drywall"     31.0  0.0
 "paint"       37.0  1.0
 "floors"      37.0  0.0
 "finish"      41.0  0.0
julia
tasks[slack .== 0]    # the critical path
9-element Vector{String}:
 "start"
 "permits"
 "foundation"
 "framing"
 "plumbing"
 "insulation"
 "drywall"
 "floors"
 "finish"
the schedule days
0510152025303540permitsfoundationframingroofplumbingelectricalinsulationdrywallpaintfloors
Each task starts at its earliest time, a row of the max-plus star. Tasks on the critical path, in red, have no slack; the grey tails show how long the others can slip.

The roof can slip two days, and the electrical work and the painting one day each. Every other task is critical.

Because the star holds every pair, other questions need no new computation: L[id["roof"], id["paint"]] is the least time between starting the roof and starting the paint, and a column of L lists everything a task waits on.

julia
L[id["roof"], id["paint"]]
13.0

A Check on a Larger Project ​

On a directed acyclic graph the longest paths from one source also follow from a single pass in topological order. Here is a random project of 2,000 tasks, numbered so that every precedence goes from a lower to a higher number, and the pass checks the first row of the star.

julia
Random.seed!(1)
m = 2000
src = Int[]; dst = Int[]; len = Float64[]
for j in 2:m, _ in 1:3
    i = rand(max(1, j - 50):(j - 1))
    push!(src, i); push!(dst, j); push!(len, rand(1:10))
end
B = sparse(src, dst, len, m, m, max)
LB = mstar(MaxPlus(), B)

longest = fill(-Inf, m); longest[1] = 0.0
for j in 2:m, p in nzrange(B, j)
    i = rowvals(B)[p]
    longest[j] = max(longest[j], longest[i] + nonzeros(B)[p])
end
LB[1, :] == longest
true

Cycles ​

A longest path is well defined only when no cycle has positive length: otherwise a path could go around it forever. In a precedence graph there are no cycles at all. If a graph has a cycle of positive length, the max-plus star is Inf for every pair whose paths can pass through it, which flags the circular dependency.

julia
C = sparse([1, 2, 3], [2, 3, 1], [1.0, 1.0, 1.0], 3, 3)    # a cycle of length 3
mstar(MaxPlus(), C)